The Children's Hospital

Miro was structural and civil engineer of record for a 1.2- million square foot inpatient and outpatient hospital, with associated clinic, pavilion and office space. The scope of work included engineering design of two multi-level parking structures for over 1,900 cars. The Miro team worked with a vibration consultant to develop specific response criteria for areas of the building according to their occupancy and operational mission.

Under the fast-track imperative of the project, the Miro structural team issued early documents, for construction at the Design Development stage. This acceleration allowed early procurement of the structural steel, during a time of price escalation,  not only saving significant material costs but also allowing an early construction start on the foundations.